June 21, 2018

Roath Flood Defence Scheme: Construction Update

I have today been contacted by Natural Resources Wales, who have updated me on the progress of the construction works.   Construction works within Railway Gardens (the Sandies) are complete, with the reinstatement and planting now well underway. Construction works in Waterloo Gardens and Roath Mill Gardens will now be focusing on the paved areas, and viewing platform / dais, …

Continue reading
March 16, 2018

Roath Flood Scheme: Phase Three PAUSED

I have today been contacted by Natural Resources Wales in regards to ‘phase 3’ of the Roath Flood Scheme. NRW have announced that they are pausing tree felling and construction for four months.   Their position is set out in full below:  We have agreed to pause tree felling and construction in Roath Brook Gardens and Roath Mill Gardens (Phase 3 of the …

Continue reading